Family houses Stupava – Zadná Street – II.phase

www.viladomystupava.sk

Family house with living spaces oriented to the South available as an unfurnished space or with the possibility of full completion in standard of traditional high-quality materials (fired bricks, roof tiles) with in-floor heating in the whole living space with own gas boiler and hot utility water heating, windows and doors of modern materials, acoustic partition walls for high acoustic comfort of living, thermal insulation of the building with thickness 12/14 cm for thermal comfort in the summer and winter, complete electrical installation including preparation for outdoor garden appliances, paved access and parking area, connection to all utility supplies.

From construction and acoustic point of view, the apartment units are separated until the top of the roof, providing the apartment unit, despite the basic usable area, with a large storage room under roof that is accessible through roof hatch ladder above the corridor of the 1st floor, and also closed storage room under staircase.

Total floor area of family house without terrace is 90,73 m2; paved floor area of terrace is 15,20 m2; total area 105,93 m2

Standards of house – villa house

Traditional materials in good quality for fair prices

At the time of concluding a Purchase Contract, the family house will be UNFURNISHED with the possibility of standard completion with following elements:

Foundations:

  • shallow strip foundations of plain concrete, width 500 mm
  • blinding concrete 150 mm, compacted gravel hardcore 100 mm
  • waterproofing bitumen membrane insulation, assembled on blinding concrete with penetrating coating

Load bearing walls:

  • outdoor load bearing masonry walls of bricks PROFIBLOK, thickness 300 mm

Ceiling construction:

  • above the ground floor, monolithic reinforced concrete slab, thickness 160 mm
  • above the first floor, wooden construction with suspended gypsum plasterboard ceiling + thermal insulation ISOVER 2×100 mm

Roof:

  • adhesively bonded timber truss
  • roofing TERRAN Danubia CS with waterproof insulation

Staircase:

  • monolithic reinforced concrete
  • L-shaped slab with concrete staircase steps

Exterior wall finishes:

  • exterior polystyrene thermal insulation, thickness 120 and 140 mm
  • facade silicone plaster, thickness 1,5 mm

Interior wall finishes:

  • lime plaster with white coating

Windows, doors and sills:

  • windows and doors in outdoor walls are designed of KBE-70 (system with closed steel profiles, in the doors is assembled metal profile with thickness 3 mm) with ROTO-NT fittings
  • thermal-insulating clear triple glazing
  • exterior aluminium window sill in the color of windows, indoor window sill of white color
  • thermal-insulated preparation for embedded blind boxes for all windows + cabling

Wall and floor tiling:

  • ceramic wall and floor tiling is not included in the scope

Heating:

  • hot-water in-floor heating of plastic-aluminium pipes
  • separate gas condensating boiler with integrated tank for hot utility water heating

Water installation and sanitary equipment:

  • hot and cold water installation, thermally insulated
  • installed flush cisterns for hanging toilet (GEBERIT)
  • the building is connected to the public water supply DN32 through common water meter shaft, where a separate water meter for the house is installed.

Sewage system:

  • plastic sewage pipes PVC DN 160, installed in wall chasing and under floor
  • sewage output is connected to the public sewage system

Gas installation:

  • gas connections DN25 installed to the boundary of individual lands for houses
  • gas meters installed in the boxes

Electrical installation:

  • complete electrical installation, including switches, sockets, home switchgear, phone, TV and lighting conductor.
  • Installed under plaster, or in the floor. Supply is solved by connecting to the existing connection through underground cabling and cabinet with the termination in the switchgear, which is installed in the fence from the side of street.
  • separate electricity meter for each apartment unit
  • electrical connection point to washing machine, electric oven and range hood
  • tube preparation for fixed phone line + 1x phone socket
  • tube preparation for TV + 1x TV socket in living room + tube preparation for cabling from the roof
  • home bell, socket on the terrace

Others:

  • Chain link fencing of the land – plastic-covered galvanized steel, dark green color
  • Surface layer of outdoor areas (terrace, parking area): block paving, or concrete blocks, grey color
  • Land shaping works in the scope of land alignment to the height of 20 cm below the groundfloor level of the building
  • Separate electricity meter, gas meter and water meter for each apartment unit
  • Mailboxes
  • Central point for rubbish bins
  • Reserved common parking slots for visitors beyond the number of own parking slots
  • Possibility of standard turnkey house at preferential conditions

The subject of Family House does not include floors, floor tiling, interior doors, door frames, wall tiling, sanitary equipment, lights, kitchenboard, furnishing, etc.

The civic amenities are at high level in Stupava. There is a kindergarten, primary school, art school, stores, market, restaurants, banks, pharmacy, health center, post office, sports facilities (football, tennis, volleyball), children’s playgrounds, pedestrian zone, pleasant sitting in a natural environment. The environment is a combination of living quality in a beautiful environment with the availability of city services nearby. Nature lovers, tourists and cyclists will be able to enjoy cycling trails from Stupava through the Morava River to Austria, the Carpathians or Bratislava, the immediate vicinity of forests offers year-round trips to the surrounding area. Smooth accessibility by car. You are in the center of Bratislava in 15 minutes via highway. This is why Stupava keeps an extraordinaly attractive position compared to other locations.

www.viladomystupava.sk

Family houses Stupava – Zadná Street – I.phase

BENEFITY

Family house with living spaces oriented to the South available as an unfurnished space or with the possibility of full completion in standard of traditional high-quality materials (fired bricks, roof tiles) with in-floor heating in the whole living space with own gas boiler and hot utility water heating, windows and doors of modern materials, acoustic partition walls for high acoustic comfort of living, thermal insulation of the building with thickness 12/14 cm for thermal comfort in the summer and winter, complete electrical installation including preparation for outdoor garden appliances, paved access and parking area, connection to all utility supplies.

From construction and acoustic point of view, the apartment units are separated until the top of the roof, providing the apartment unit, despite the basic usable area, with a large storage room under roof that is accessible through roof hatch ladder above the corridor of the 1st floor, and also closed storage room under staircase.

Total floor area of the semidetached family house without terrace is 90,73 sqm; paved floor area of terrace is 15,20 sqm; total area 105,93 sqm

Equipment of the house

Traditional materials in perfect quality for fair prices

At the time of concluding a Purchase Contract, the family house is offered as UNFURNISHED having an option of a completion with following standard features:

Foundations:

  • shallow strip foundations of plain concrete, width 500 mm
  • blinding concrete 150 mm, compacted gravel hardcore 100 mm
  • waterproofing bitumen membrane insulation, assembled on blinding concrete with penetrating coating

Load bearing walls:

  • outdoor load bearing masonry walls of bricks type: PROFIBLOK, thickness 300 mm

Ceiling construction:

  • above the ground floor, monolithic reinforced concrete slab, thickness 160 mm
  • above the first floor, wooden construction with suspended gypsum plasterboard ceiling + thermal insulation ISOVER 2×100 mm

Roof:

  • adhesively bonded timber truss
  • roofing TERRAN Danubia CS with waterproof insulation

Staircase:

  • monolithic reinforced concrete
  • L-shaped slab with concrete staircase steps

Exterior wall finishes:

  • exterior polystyrene thermal insulation, thickness 120 and 140 mm
  • facade silicone plaster, thickness 1,5 mm

Interior wall finishes:

  • lime plaster with white coating

Windows, doors and sills:

  • windows and doors in outdoor walls are designed of KBE-70 (system with closed steel profiles, in the doors is assembled metal profile with thickness 3 mm) with ROTO-NT fittings
  • thermal-insulating clear triple glazing
  • exterior aluminium window sill in the color of windows, indoor window sill of white color
  • thermal-insulated preparation for embedded blind boxes for all windows + cabling

Wall and floor tiling:

  • ceramic wall and floor tiling is not included in the scope

Heating :

  • hot-water in-floor heating of plastic-aluminium pipes
  • separate gas condensating boiler with integrated tank for hot utility water heating

Water installation and sanitary equipment:

  • hot and cold water installation, thermally insulated
  • installed flush cisterns for hanging toilet (GEBERIT)
  • the building is connected to the public water supply DN32 through common water meter shaft, where a separate water meter for the house is installed.

Electrical installation:

  • complete electrical installation, including switches, sockets, home switchgear, phone, TV and lighting conductor.
  • Installed under plaster, or in the floor. Supply is solved by connecting to the existing connection through underground cabling and cabinet with the termination in the switchgear, which is installed in the fence from the side of street.
  • separate electricity meter for each apartment unit
  • electrical connection point to washing machine, electric oven and range hood
  • tube preparation for fixed phone line + 1x phone socket
  • tube preparation for TV + 1x TV socket in living room + tube preparation for cabling from the roof
  • home bell, socket on the terrace

Sewage system:

  • plastic sewage pipes PVC DN 160, installed in wall chasing and under floor
  • sewage output is connected to the public sewage system

Gas installation::

  • gas connections DN25 installed to the boundary of individual lands for houses
  • gas meters installed in the boxes

Others:

  • Chain link fencing of the land – plastic-covered galvanized steel, dark green color
  • Surface layer of outdoor areas (terrace, parking area): block paving, or concrete blocks, grey color
  • Land shaping works in the scope of land alignment to the height of 20 cm below the groundfloor level of the building
  • Separate electricity meter, gas meter and water meter for each apartment unit
  • Mailboxes
  • Central point for rubbish bins
  • Reserved common parking slots for visitors beyond the number of own parking slots
  • Possibility of standard turnkey house at preferential conditions

The subject of Family House does not include floors, floor tiling, interior doors, door frames, wall tiling, sanitary equipment, lights, kitchenboard, furnishing, etc.

More on www.viladomystupava.sk

Roads and sidewalks

The project deals with the road of class C3, category MO 7,5/40 and MOU 6,5/30 (STN 736110) and sidewalks, for individual construction of family houses in 27 lands.

  • road of class D1
  • category MO 6,5/40 – 312,5m
  • sidewalk of width 1,50m and in total length 315,00 m.
  • sidewalk of width 2,00m and in total length 287,35

block paving 60 mm
sub-base (sand or mortar) 40 mm
high-performance concrete 100 mm
compacted crushed rock hardcore 150 mm
________________________________________________

Total thickness:  350 mm

  • Crossing of sidewalks with OS2 and OS3 with barrier-free adjustment under the Decree No. 192/94 Coll.

VILA HOUSES, Na Vyhliadke Street – 2.phase

Exclusive terraced family houses with own garden in an outstanding environment near the forest in Stupava, in a new location in the street Na Vyhliadke.

Family house with living spaces oriented to the South available as an unfurnished space or with the possibility of full completion in standard of traditional high-quality materials (fired bricks, roof tiles) with in-floor heating in the whole living space with its own gas boiler and hot utility water heating, windows and doors of modern composite materials, acoustic partition walls for high acoustic comfort of living, thermal insulation of the building with thickness 12 cm for thermal comfort in the summer and winter, complete electrical installation including preparation for outdoor garden appliances, paved access and parking area, connection to all utility supplies.

Both the building and the acoustics are separated from each other up to the level of the roof, whereby the housing unit, in addition to the basic utility area, has a generous storage space under the roof, accessible to the 1st storey as well as a closed chamber in the space below the staircase.

Total floor area of family house without terrace is 90,73 m2; paved floor area of terrace is 15,20 m2; total area 105,93 m2.

Standards of house – villa house – Traditional materials in good quality for fair prices

At the time of concluding a Purchase Contract, the family house will be UNFURNISHED with the possibility of standard completion with following elements:

Foundations:

  • shallow strip foundations of plain concrete, width 500 mm
  • blinding concrete 150 mm, compacted gravel hardcore 100 mm
  • waterproofing bitumen membrane insulation, assembled on blinding concrete with penetrating coating

Load bearing walls:

  • outdoor load bearing masonry walls of bricks PROFIBLOK, thickness 300 mm

Ceiling construction:

  • above the ground floor, monolithic reinforced concrete slab, thickness 160 mm
  • above the first floor, wooden construction with suspended gypsum plasterboard ceiling + thermal insulation ISOVER 2×100 mm
  • vyvedenie kanalizácie je riešené do obecnej kanalizačnej siete

Roof:

  • adhesively bonded timber truss
  • roofing TERRAN Danubia CS with waterproof insulation

Staircase:

  • monolithic reinforced concrete
  • L-shaped slab with concrete staircase steps
  • Exterior wall finishes
  • exterior polystyrene thermal insulation, thickness 120 and 140 mm
  • facade silicone plaster, thickness 1,5 mm

Interior wall finishes:

  • lime plaster with white coating

Windows, doors and sills:

  • windows and doors in outdoor walls are designed of KBE-70 (system with closed steel profiles, in the doors is assembled metal profile with thickness 3 mm) with ROTO-NT fittings
  • thermal-insulating clear triple glazing
  • exterior aluminium window sill in the color of windows, indoor window sill of white color
  • thermal-insulated preparation for embedded blind boxes for all windows + cabling

Wall and floor tiling:

  • ceramic wall and floor tiling is not included in the scope

Heating:

  • hot-water in-floor heating of plastic-aluminium pipes
  • separate gas condensating boiler with integrated tank for hot utility water heating

Water installation and sanitary equipment:

  • hot and cold water installation, thermally insulated
  • installed flush cisterns for hanging toilet (GEBERIT)
  • the building is connected to the public water supply DN32 through common water meter shaft, where a separate water meter for the house is installed.

Sewage system:

  • plastic sewage pipes PVC DN 160, installed in wall chasing and under floor
  • sewage output is connected to the public sewage system

Gas installation:

  • gas connections DN25 installed to the boundary of individual lands for houses
  • gas meters installed in the boxes

Electrical installation:

  • complete electrical installation, including switches, sockets, home switchgear, phone, TV and lighting conductor.
  • Installed under plaster, or in the floor. Supply is solved by connecting to the existing connection through underground cabling and cabinet with the termination in the switchgear, which is installed in the fence from the side of street.
  • separate electricity meter for each apartment unit
  • electrical connection point to washing machine, electric oven and range hood
  • tube preparation for fixed phone line + 1x phone socket
  • tube preparation for TV + 1x TV socket in living room + tube preparation for cabling from the roof
  • home bell, socket on the terrace

Others:

  • Chain link fencing of the land – plastic-covered galvanized steel, dark green color
  • Surface layer of outdoor areas (terrace, parking area): block paving, or concrete blocks, grey color
  • Land shaping works in the scope of land alignment to the height of 20 cm below the groundfloor level of the building
  • Separate electricity meter, gas meter and water meter for each apartment unit
  • Mailboxes
  • Central point for rubbish bins
  • Reserved common parking slots for visitors beyond the number of own parking slots
  • Possibility of standard turnkey house at preferential conditions

The subject of Family House does not include floors, floor tiling, interior doors, door frames, wall tiling, sanitary equipment, lights, kitchenboard, furnishing, etc.

Gas pipeline with connections

The project deals with the gasification for new residential zone in the South-West of Stupava for individual construction of family houses in 27 lands.

Gas pipeline with connections

  • Gas pipeline PE D 90×8,2 length – 301,97 m
  • Gas pipeline PE D 50×4,6 length – 110,83 m
  • Gas connections   PP PE D 32×2,9 length – 144,69 m – 29 pcs
  • Fine sand bed with thickness 0,3 m
  • Pipe installed with tracer wire according to the standard STN 347420, PVC-insulated wire of CY type with minimum cross-section 4,0mm2

Public street lighting

The project deals with wires, poles and arms of public street lighting for new residential zone in the South-West of Stupava for individual construction of family houses in 27 lands.

  • Length 484 m
  • Light source MALAGA
  • 15 pcs of poles height = 5 m

Public water supply

The project deals with drinking water supply for new residential zone in the South-West of Stupava for individual construction of family houses in 27 lands.

Public water supply with connections consists of:

  • HDPE pipeline 110×6,6 mm – length 305,32m
  • HDPE connections 40×2,4 mm – length 58 m
  • HDPE connections 32×2 mm – length 126 m
  • Underground fire hydrant DN80 – 3 pcs
  • Aboveground fire hydrant – 1 pc

Public rainwater sewage system

The project deals with the construction of public sewage system and road gullies of rainwater sewage system for residential zone in the South-West of Stupava for individual construction of family houses in 27 lands.

  • Public rainwater sewage system with road gullies – length 252m
  • Drainage shafts with depth 5 m – 4pcs under the road.
  • Road gullies – 4 pcs
  • Sewage maintanance shafts – 4 pcs

Public sewage system

The project deals with the construction of public sewage system and branches, for new residential zone in for residential zone in the South-West of Stupava for individual construction of family houses in 27 lands.

Public sewage system with connections consists of:

  • PVC pipeline DN300 with length 428,0 m (gravitational section),
  • Connecting pipeline DN160, 20 pcs
  • 13 pcs of maintenance sewage shafts DN1000 mm of precast concrete blocks with manhole DN600 mm and manhole cover DN600 mm.
  • Pipeline is placed on compacted sand sub-base in a trench of width 1 m secured with shoring and backfilled with sand to the height 30 cm above the pipeline

Roads and sidewalks

The project deals with the road of class C3, category MO 7,5/40 and MOU 6,5/30 (STN 736110) and sidewalks on the eastern border of Stupava, in the district of Kremenica on the hill near the forest, for individual construction of family houses in 23 lands.

  • road of class C3
    • category MO 8,5/40 – 101m
    • category MO 7,5/40 – 182m
    • category MOU 6,5/30 (STN 736110) – 101m
  • sidewalk of width 1,75m and roads of width 7,50 m in total length 280,00 m
  • block paving 60 mm
  • sub-base (sand or mortar) 40 mm
  • high-performance concrete 100 mm
  • compacted crushed rock hardcore 150 mm

_________________________________________________

Total thickness:  350 mm

  • Crossing of sidewalks with OS2 and OS3 with barrier-free adjustment under the Decree No. 192/94 Coll.